Construction Update

Dec 16, 2019

The Mandelbaum Gate provides a beautiful entry to Mesivta’s campus, complementing the stunning frontage provided by the Lainer/Friedman Family Bais Medrash.

Mesivta has a full crew working on the next phase of our campus expansion; the Alon & Rosana Miller and 2 other Dormitory buildings!

All three dormitories framing, roofing, and dry wall are under process and we’re on track for a June completion date with an Elul 5780 (August 2020) move in scheduled.